Renovation Plans for 2010
Master Plan Underway
The trustees have worked closely with Architect, John Cole, to develop a “master plan” for building renovation and redevelopment to align our facilities with the needs of our mission and ministry. This process involved many of the church's members to gather their input and now, the final drawings may be viewed on the bulletin board near the soda machine on the first floor.
Key Dates on the Timeline
- February 28, 2007 approval was given by the Bi-District Church Location and Building Committee to move forward with the Renovation Plans.
- A Church Conference was held on Sunday, March 4, 2007 and final approval for a line of credit was unanimously supported by all who attended.
- A Town Hall meeting was held on Wednesday, June 20, 2007 in Fellowship Hall at 6:30 pm to share preliminary Master Plans for Fellowship Hall renovations. Conceptual plans were supported by the congregation.
- February 10, 2008 Town Hall meeting to share final Master Plans with the congregation.
- February 29, 2008 tentative closing date for the sale of the parking lot.
- June - July, 2008 fellowship hall renovations were completed with the addition of a new sound booth, two 50-inch flat screens, and a storage closet.
- February - March 2009 kitchen work began to replace the hood over the stove, several pieces of equipment, and painting.
- Phase One Began on October 26, 2009 and is completed in February 2010. Phase One included replacing the Sanctuary air handling unit, Balcony renovation, and Boiler room work;
- Phase Two began in April 2010 and includes exterior waterproofing / foundation repairs; completion of the PVC project and/or painting of exterior trim, and Asbestos abatement in the basement as finances allow.
If you have any questions about this initiative, please contact Ken Young, Trustees Chair, at the church office.